Short answer: in Karnataka a promoter must deposit 70% of what allottees pay, net of GST and pass-through charges, into a no-lien RERA designated account. Money comes out only against three certificates: the architect's Form-5, the engineer's Form-6 and the chartered accountant's Form-4. The CA's Form-4 sets the cumulative ceiling at total estimated project cost × the lower of the architect's percentage of completion and the CA's percentage of cost incurred. What has already been withdrawn is deducted. Land paid for early does not raise that ceiling on its own.
Where the rule comes from
Section 4(2)(l)(D) of the Real Estate (Regulation and Development) Act 2016 ("the Act") requires the promoter to declare, when registering, that 70% of the amounts realised from allottees will be deposited in a separate account with a scheduled bank. The money is there to cover the cost of construction and the land cost, and may be used only for that purpose. Three provisos follow:
- Withdrawals must be in proportion to the percentage of completion of the project.
- Each withdrawal must first be certified by an engineer, an architect and a chartered accountant in practice.
- The accounts must be audited within six months of each financial year end, and the audit must confirm both points above. In Karnataka that audit is Form-7, covered in the annual audit report.
The Explanation to the clause defines only "scheduled bank". "Land cost" and "cost of construction" are defined in the state rules. The Karnataka mechanics sit in four instruments:
| Instrument | What it settles |
|---|---|
| Karnataka Real Estate (Regulation and Development) Rules 2017, Rule 4(5) and Rule 5 | The 70%/100% rule for ongoing projects; what land cost and cost of construction mean |
| Karnataka RERA (General) Regulations 2022, Regulations 3 and 29 | Form numbering, who signs, the no-lien account, fixed deposits, change of bank |
| Karnataka RERA Bank Account Directions 2020 (Circular RERA/Finance-Section/BAD/02/2020-21, 07.01.2020) | The withdrawal procedure and the three certificates |
| Form-4 as published by K-RERA | The actual computation of the withdrawable amount |
The account: one per project, no lien, no loan
Regulation 29 sets out how the account must be kept:
- One RERA Bank Account for each registered project, opened before the registration application in a scheduled bank's local branch where the project is being built. The account name carries the suffix "RERA Designated Account", e.g. ABC-RERA Designated Account of XYZ.
- It is a no-lien account: no third-party rights or security interests.
- Balances may go into a fixed deposit with the same bank, but only as a no-lien fixed deposit. No loan against it, no charge on it. Where there is a fixed deposit, a no-lien certificate from the bank is obtained every three months and filed with the quarterly return.
- The bank can be changed only with the Authority's prior permission, using the Form-B series of applications and bank certificates.
Collection, designated and current accounts. The Regulations require just one RERA Bank Account per project. K-RERA's published Form-4 and Form-7 templates, though, ask for details of three: a RERA Project Collection Account (100%), the RERA Designated Account (70%) and a RERA Current Account of the Builder (30%). Many banks run exactly that sweep. It is an operating arrangement the forms expect, and it does not replace the designated account. MahaRERA made the three-account structure compulsory from 1 July 2024. Karnataka has not.
Joint developments. Under K-RERA Circular 03/2019 (31 October 2019), a landowner who takes an area or revenue share is treated as a promoter. If a landowner sells units from their share before the completion or occupancy certificate, 70% of those sale proceeds also go into the project's designated account. The developer is expected to make sure this happens. That term belongs in the joint development agreement. See the twelve JDA clauses worth negotiating.
70% or 100%: what goes in
The deposit base is the amount collected from allottees other than pass-through charges and indirect taxes (Regulation 29(3)). GST is excluded. The Regulations do not define "pass-through charges". The workable reading covers amounts collected only to be paid on to a government body or utility, such as stamp duty and registration fees. Record the basis you apply, because the auditor will ask for it.
For ongoing projects (projects already under way when they were registered), Rule 4(5) raises the deposit to 100% where the project's remaining receivables are less than the estimated cost of balance construction. Form-4 runs this test every quarter in its Additional Information section:
| Line | How it is computed |
|---|---|
| (1) Estimated balance cost to complete | Total estimated cost less cost incurred |
| (2) Balance receivable from units sold | From agreements, verified by the CA |
| (3) Estimated proceeds of unsold units | Unsold carpet area × ready-reckoner (guidance) rate, as on the certificate date |
| (4) Estimated receivables | (2) + (3) |
| Result | If (4) exceeds (1): 70%. If (4) is less than (1): 100% |
A project whose unsold stock is thin and whose costs have overrun can move to 100% partway through. The CA's certificate is where that surfaces first.
What counts as land cost and construction cost
Rule 5 of the Karnataka Rules and the Form-4 line items together give the heads that count towards withdrawal.
| Counts as land cost | Counts as cost of construction / development |
|---|---|
| Cost of acquiring ownership and title (outright purchase, lease, etc.) or the guidance value under section 45-B of the Karnataka Stamp Act 1957 on the date of project registration, whichever is higher | Construction cost, taking the lower of the engineer-certified figure and the actual cost in the books |
| Purchase of TDR (transferable development rights) | On-site expenditure: salaries, consultants' fees, site overheads, development works, services (water, electricity, sewerage, drainage, layout roads), machinery hire and maintenance, consumables |
| Approval fees, NOCs, stamp duty, transfer and registration charges, conversion charges, statutory payments to state and central government | Off-site development expenditure (Rule 5(2)) |
| Taxes, cess, fees, charges, premiums and interest paid to any statutory authority | |
| Interest to banks, financial institutions, NBFCs or lenders on construction funding |
Some costs are not on either list and should not go into the Form-4 figure. Marketing and advertising, brokerage and channel-partner commission are not listed. Neither are head-office overheads (Form-4 speaks of costs "directly incurred" to complete the construction), or interest on borrowings not raised for construction. Income-tax, costs of other projects, and land held for phases outside this registration are also excluded.
Form-7, the annual statement, adds two lines: other land-related cost (including interest on land borrowings) and administrative and management expenses. The annual cost table and the quarterly computation will not always match line by line, so keep a reconciliation.
The guidance-value limb is particular to Karnataka and matters most in a joint development, where the developer pays little or no cash for the land. The estimated land cost is fixed at registration and runs through every later Form-4, so decide how it is measured before the project is registered, not in the first withdrawal quarter.